Annex A
(informative)
Example of a form for the preliminary information on the intended sampling and groundwater measurements
Preliminary information on the intended sampling and groundwater measurements | ||
Project | ||
Location | ||
Number of boreholes, excavations and/or groundwater measurements | ||
Orientation, inclination and acceptable deviations in boreholes | ||
Surveying requirements and expected geological and hydrogeological conditions | ||
Required accuracy and uncertainty of measurements | ||
Frequency of measurements | ||
Environmental and safety risks (associated with, e.g. flushing media, suspensions) | yes | no |
If yes, please specify | ||
Hazardous assessment for contaminated sites | done not done not known not necessary | |
Possible risks | yes | no |
If yes, please specify underground services, such as..................................................................... overhead services, such as............................................................................ traffic, such as................................................................................................. unexploded ordnance..................................................................................... contamination, such as................................................................................... other, such as................................................................................................. ................................................................................................................................ |
||
Planned depth of the borehole or excavation | ||
Sampling category | A B C | |
Sampling method(s) | ||
Sample handling | ||
Sample storage | ||
Sample transport | ||
Intended in situ testing | yes | no |
If yes, please specify standard penetration test o borehole expansion tests, such as................. geophysical borehole tests, such as............................................................ geohydraulic tests, such as............................................................................ piezometer installation................................................................................... other, such as................................................................................................... ................................................................................................................................ |
||
Borehole completion method and site reinstatement (needs, material, methods, etc.) | ||
Environmental care | ||
Emergency arrangements | ||
Name of the contact person (client or representative) | ||
Flow of information | ||
Name of qualified operator | ||
Name of responsible expert | ||
Remarks |